Does your cycle store work in the real world, not just on paper?

article

We sat down with Alex Gent to find out how Bellsure turns cycle parking ideas into layouts that actually work on site.

Alex, can you tell us a bit about your role at Bellsure?

Alex: I’m the Computer Aided Design Manager – part of a team that’s responsible for turning briefs into workable drawings and models. On the 3D side I’m working on things like sheet metal parts, frames, weldments, assemblies and mesh panels. On the 2D side I’m planning out cycle stores – things like where the racks go, how shelters fit, or whether door widths and aisles work in practice.

OK, so at what stage of the project do you usually get involved?

Alex: At one end of the spectrum we’ll have architects approaching us very early, sometimes before the scheme designs have been submitted – and at the other end, we might get the call when the main contractor is live on site and there’s a problem.

What sorts of problems do you get?

Alex: There’s sometimes an assumption that cycle storage is an easy package – and it can be, if the store works. When it doesn’t, we do a lot of work to make it fit. A classic example is overhead services like ducts and cabling that didn’t appear in the drawings – then our installers will be calling from the site saying, “there’s a duct here we didn’t know about”, and we’ll need to quickly redesign the store around it so the scheme still works.

When we talk about “cycle space planning”, what does it actually mean?

Alex: We take the architect’s plan and make sure the layout works for our products and the people using the space. So that’s the right mix of stand and racks, with the right aisle widths and clearances and making sure the space is accessible – all in line with the standards they need to meet.

And then we’re creating the actual drawings and models that everyone else uses – so that’s 2D plans in AutoCAD, 3D models in Inventor, and BIM-ready content in Revit where needed. We supply CAD blocks and spec sheets so architects can plan their early layouts more accurately. The more we can give them up front, the more likely it is that the store they’ve sketched will work in reality when it gets to us.

So who do you typically work with?

Alex: It varies. Architects will usually come to us early for guidance – they’ll be thinking about compliance, capacity and how the store ties in with their overall scheme. We also do a lot of work with technical coordinators and design managers on the contractor side, helping them to solve very practical problems quickly, so the programme doesn’t slip.

But the common thread is that they need us to translate numbers and standards into a layout that works on site, not just on paper.

What does a typical brief look like?

Alex: Ideally, we’ll get a DWG drawing of the store, but sometimes it’s a PDF or another editable file format. We’ll also get information on the planning context. For example, we might be told that the scheme needs to comply with a specific council’s cycle parking requirements, or with London Cycle Design Standards.

Sometimes we’ll also get a spreadsheet showing how many spaces are required per block, or a marked-up plan with different stores highlighted for different parts of the development. All of that helps us make sure each layout delivers what’s needed for that specific building.

What do you actually send back to the client, and how quickly?

Alex: Most of the time, it’s a PDF drawing of the store in plan view, showing the room outline and surrounding context, rack types and positions, aisle widths and clearances, and quantities by rack type and store. Essentially it gives something concrete for the client to approve – the layout, the colour, the number of spaces. It’s a big part of how we avoid confusion later.

On simpler jobs, we can turn a layout around in a day. Others involve a lot more back-and-forth, 3D modelling and discussion. It really depends on the complexity.

How often do layouts have to change – and how do you manage that?

Alex: Changes happen, but we always find solutions. We recently planned two-tier racks for a store, but when we surveyed the site, it turned out all the overhead services were below our 2.4m minimum – which meant two-tier was a non-starter.

We redesigned the store with semi-vertical racks instead, not ideal but far better than installing something that simply wouldn’t work. Our client could then have a sensible conversation with their planning officer backed up by a clear drawing of the revised, workable layout.

What do you mean by a 2.4m minimum?

Alex: If we’re not working to a named standard, we always work to our own tried and tested minimums. For example, from years and years of experience, we know that ideally you need 2.6m clear height over a two-tier system to cater for tall bikes, and that 2.4m is the absolute minimum workable height. Below that height, two-tier racks are not an option.

If you had to explain why someone should use Bellsure’s design service, what would you say?

Alex: We’ve got the experience to look at a drawing and understand whether the product will work in the planned configuration. Will it actually fit? At the end of the day, because we design, supply and also install cycle parking systems, we’re fully invested in making sure the layout we agree is one that can be built and used effectively.

Finally, what’s the one piece of advice you’d give architects about cycle space planning?

Alex: I’d say think about a real bike being wheeled through the door, turning in the space and being loaded onto the rack – then taken down again and wheeled back out.

Think about handlebars and saddle height. Taller people have taller bikes – it sounds obvious but it’s important to remember! If you visualise the bike rather than just the spacing on a drawing, you’re much more likely to end up with a store that people can actually use in practice.

And it’s worth saying we’re always happy to get involved early. The more we can help shape the store up front, the less stress there is when the building is close to handover.

If you want to be sure your cycle storage will work in practice, share your plans with us today.

If you’re planning a new scheme, send us your drawings and let us do the rest. Our in-house CAD team will sense-check the space, optimise the layout and make sure it works for real bikes, real people and real site conditions.

Be sure with Bellsure

If you’re planning an upcoming development or refining a live scheme, it’s worth bringing cycle parking, shelters and shared-space infrastructure into the conversation early – so the final 10% becomes a smooth handover, not a scramble.

It’s not that cycle storage or end-of-journey provision is uniquely difficult. But they are late enough in the project sequencing to be under time pressures, visible enough to matter to stakeholders and the wider public, and interconnected enough to create knock-on risks if delivery and the quality of the solution is weak.

At Bellsure, we anticipate constraints, communicate clearly, stay flexible, and deliver exactly what we promise. Quite simply, choosing Bellsure makes the final stages of your project easier.

Explore our product range or speak to the team today to find out how we can support your next project.